Aioi Nissay Dowa
Our Approach
Due to the lift restrictions, Technimove advised AND-E that the rack could not be moved fully populated and that devices would need to be removed before the rack could be wheeled to the lift. It was also impossible to securely transport the rack up the stairs without compromising safety.
1.
Pre-Migration Activity
A Technimove Project Manager worked alongside AND-E to create a detailed migration plan. The project manager needed to take account the lengthy journey from London to Munich whilst sticking to tight migration timelines.
Technimove’s Warehouse team used measurements that were taken during the site survey to build bespoke ramps, in order to negotiate the steps outside the building and inside the data hall.
2.
Migration
On the Migration day, the Technimove team arrived onsite ahead of time to complete a final assessment of the work and prepare the environment. Spreader plates were laid down from the Data Hall to the loading bay to ensure that the flooring is not damaged whilst moving heavy equipment. Once all the equipment had been powered off, the Technimove team secured the rack in a purpose built rack jacket. Technimove’s rack jackets are foam-protected and water resistant. Once the rack was secured, the team wheeled the rack to the exit before loading it into an 18tonne truck via tail lift.
Once all equipment was loaded, the team commenced the journey to Munich.
Considering the distance of travel and HGV driving hour limitations, a separate Technimove team was flown to Munich in order to reduce the migration downtime.
Once the equipment arrived at the delivery site, the equipment was handed over to the second team. Technimove engineers placed the purpose built ramps and wheeled the rack inside the building. Once inside and protected from bad weather, the team labelled all cables inside the rack before decommissioning the equipment.
Once the rack was lighter and adhering to the lift’s weight restriction, it was wheeled into the lift and transported to the third floor. The removed devices were secured into flightcases and were also transported to the third floor. When the equipment reached the third floor, the Technimove team wheeled it out of the lift and placed it in front of the data hall door. The team placed the purpose built ramp down on the step before wheeling the rack and flightcases up to the data hall.The team then pushed the rack into place. The devices were then re-racked and patched back to their original arrangement. Once the rack was in place, AND-E signed off the project, confirming a successful migration.